Item Task
01 Technical upgrade on New server
-Duplicate R/3 4.71 system to new server
-Uni-code conversion
-Database upgrade
-R/3 4.71 system upgrade to ECC 6.0 system
02 各模組日常作業(Daily operation test) & Master data Standard programs(per role)
03 各模組日常作業(Daily operation test) Addon programs
04 各模組日常作業(Daily operation test) Interface
05 IMG 修改,Addon 程式修改
06 Logistics整合測試
07 FI/CO月結測試
08 各模組日常作業(Daily operation test) Addon program(修改後)
09 New Version Go_live Preparation
10 Upgrade R/3 4.71 PRD system to New ECC6.0 system
11 Go-Live
12 IFRS change if required